We started this project on 15th September. Progress is going well.
Work on the tiling in the new bathrooms has started and some of the plastering has been done. The windows are being fitted in the next week. All the electrics, pipework, new boiler works are currently being done.
The new windows were fitted on 27th and 28th November. The painters are in right now and in January we will fit the kitchen, the wooden flooring, the woodwork and carpentry will also be done. By the end of January all will be complete as we will be taking a break over the Christmas period.
Please see some recent photos attached.