19th March: Progress continues to be good at the loft. We had 5 men working on the site in SW11 today. The roof joists and floor are taking shape. The staircase up to the loft has been built. This was made from pine rather than MDF and it mirrors the existing staircase below. Dimitri is busy doing the pointing on the eternal brickwork. The dividing wall to the old kitchen has been removed and one can really see how the new kitchen / living room / dining room will look. Please see some photos below taken today.