The roof is now complete on this London loft conversion. The scaffold cannot come down yet until the bathroom window and the sash window in the top loft room have been fitted. The late delivery of these items are delaying us. The drain at the bottom of the external steps has to be finished also before the roof comes off. Any rain coming falling down these steps will drain away through this drain – it is vital that this does not leak – we have to get this right.
The plasterers are coming in this week and the external rendering will be done also.
We are now in the final phase. The new central heating system will be fitted together with all the radiators. The gas fired burner has been fitted and the kitchens and bathrooms will soon also be completed together with the decorating. We are on schedule…