Progress has been swift, the weather has been hot, we have had 7 men working on this project since we started on 12th August, 2013. The loft staircase is being fitted on 12th September, the tin roof on the scaffold […]
Progress has been swift, the weather has been hot, we have had 7 men working on this project since we started on 12th August, 2013. The loft staircase is being fitted on 12th September, the tin roof on the scaffold […]
Our client in Battersea sent in this cracking photo of the roof terrace we built over the summer as part of a complete loft conversion / refurbishment project over the summer. What a view! We are jealous! The roof terrace […]
We are making quite a few bespoke cupboards for one particular client in Queens Club Gardens. In the ensuite bathroom, we have made a double basin unit which will have a marble top fitted. In the bedroom we are making […]
On Monday 12th August, we started an exciting loft and kitchen side return in Southfields near Wimbledon and Earlsfield in London. We have a strict deadline to have this completed by Christmas. Please watch this space for news and photos […]
I have been taking photos at different stages of a complete refurbishment we did in Westminster. Last week, I went to take some completed photos. Please see a selection of photos that were taken throughout the job including some completed ones.
The roof is now complete on this London loft conversion. The scaffold cannot come down yet until the bathroom window and the sash window in the top loft room have been fitted. The late delivery of these items are delaying […]
We have been trying a new roofing technique on the loft conversion we are doing in Battersea / Clapham.
We are currently re-tiling / re-vamping 5 bathrooms in Rogate / Sussex. This is the second one – we added a VELUX window to bring more light into the existing bathroom and all this natural light has improved the bathroom […]
We are often asked to make radiator covers in London. Here is a photo of one we have made on a project we are doing in Westminster together with it fully installed in the kitchen…
22nd March: Even though it is cold, moral continues to be good. The guys were singing when I arrived on the site today. We met with the Building Control Officer and he was happy with the structural side of things. His next visit will be to sign off the insulation once this has been done. The lower bathroom was completely stripped out today which is great. The roof joists are in lunch was cooking on the hob when I arrived!
Please check out the photos from today…